User Story
As a Counselling Officer, I want to record a confirmed TB case's Type of Treatment and its corresponding regimen, so that the correct regimen options are offered and expected treatment completion is calculated correctly.
IMPORTANT - supersedes previous scope
This ticket previously specified a single flat regimen list (DS-TB / Shorter / Longer / BPaL / INH Mono). Per the updated PRD (Section 7.3) that model is REPLACED by the two-tier structure below. Do not build the old flat list.
Field Specifications
| Field | Type | Options | Logic / Validation |
|---|---|---|---|
| Type of Treatment | Radio button | DS TB, PMDT | Single selection. If DS TB then enable "DS TB Regimen". If PMDT then enable "PMDT Regimen". |
| DS TB Regimen | 2 HRZE/4HRE | Enabled only if Type of Treatment = DS TB | |
| PMDT Regimen | Dropdown | Regimen for H mono/Poly; Longer M/XDR-TB Regimen; Shorter MDR/RR TB Regimen; BPaLM/BPaL Regimen | Single selection. Enabled only if Type of Treatment = PMDT |
| Treatment Start Date | Date picker | Mandatory. Must be on or after TB Identification and Diagnosis Visit Date. Not greater than today. | |
| Expected Treatment Completion Date | Label (read-only) | Auto-calculated | Auto-calculate from Treatment Start Date based on regimen type - see open question below |
Acceptance Criteria
- [ ] "Type of Treatment" radio renders with exactly two options: DS TB, PMDT (single-select, mandatory)
- [ ] Selecting DS TB enables "DS TB Regimen" (value 2 HRZE/4HRE) and hides/disables "PMDT Regimen"
- [ ] Selecting PMDT enables the "PMDT Regimen" dropdown with all four options and hides/disables "DS TB Regimen"
- [ ] Switching between DS TB and PMDT clears any previously selected regimen value from the other branch
- [ ] Treatment Start Date validations enforced (on or after diagnosis visit date, not future, mandatory)
- [ ] Expected Treatment Completion Date is read-only and auto-recalculates whenever regimen or start date changes
- [ ] Selected values persist and drive the follow-up cadence / completion thresholds used by
STOP-41andSTOP-42 - [ ] Existing behaviour retained: when a DS-TB case is confirmed, the household contact tracing / TPT flow is triggered with the "screen all household contacts" prompt
OPEN QUESTION - blocks completion of the auto-calc rule
The PRD (Section 7.3) leaves the completion-date durations incomplete - it states "If Regimen Type is DS-TB then add *" and "If Regimen Type is PMDT, then add *" with no values filled in. Exact month durations per regimen are needed from the product/clinical owner before the Expected Treatment Completion Date calculation can be implemented.
Note also that the downstream completion thresholds in STOP-42 (enable completion question after 5 / 9 / 18 monthly follow-ups) are keyed to the OLD regimen numbering and will need remapping to the new DS TB / PMDT regimen set.
PRD Reference
TBMJA PRD - Section 7.3 Confirmed TB Cases - Treatment and Follow-Up
https://pmp.piramalswasthya.org/confluence/spaces/AMRIT/pages/149487638/TBMJA+PRD